Roadmap

The project’s planned implementation timeline. This page is updated as the current phase changes.

  1. 2025 – 2026 · 15 mo

    Project Preparation

    Project design, technical planning and permitting.

  2. 2027 · 12 mo

    Construction & Installation

    Facility buildings, extraction line and laboratory installation.

  3. Jan – May 2028 · 5 mo

    Trial Production

    Process validation, quality control and finalisation of product specifications.

  4. Jun 2028 → · Ongoing

    Full-Scale Production

    Targeting regular supply to domestic and international markets.

0115 mo

2025 – 2026

Project Preparation

Project design, technical planning and permitting.

0212 mo

2027

Construction & Installation

Facility buildings, extraction line and laboratory installation.

035 mo

Jan – May 2028

Trial Production

Process validation, quality control and finalisation of product specifications.

04Ongoing

Jun 2028 →

Full-Scale Production

Targeting regular supply to domestic and international markets.

This is the planned project timeline; commercial production remains subject to project implementation and commissioning.